Many solar models start with a capacity figure and a tariff, and then run forward for 25 years. That shortcut hides the questions that decide whether a project is bankable: how much the plant will actually generate, what the power purchase agreement (PPA) allows the project to earn, how much equity a lender expects, and which tax benefits still apply under the rules in force today. Developers in Ahmedabad and Vadodara, lenders in Mumbai and advisers in Gurugram each test a different part of the same model. Below we set out how to build the model so that each part can be checked on its own.
Key takeaways
- Tie revenue to the contracted tariff and the energy the PPA allows the plant to sell. A capacity figure alone does not produce revenue.
- Build CAPEX per MW from quotes for modules, inverters, balance of system and the EPC contract, and show each as its own line so the sensitivity to module prices is visible.
- Take CUF from a site-specific yield study, then apply degradation from the module warranty rather than one flat figure over 25 years.
- Report project IRR and equity IRR separately. The first tests the asset, and the second tests what the sponsor receives after debt.
- Check every tax benefit and subsidy against the current law and the scheme text before it enters the cash flow.
The Framework of a Renewable Energy Project Model
A solar project model runs for the life of its PPA, usually around 25 years, and links four inputs: the energy the plant produces, the tariff paid for each unit, the capital cost and the operating cost. Lenders and tax rules sit on top of these four inputs. Keep the structure in that order so that each link can be tested on its own.
Understanding the 25-Year Project Lifecycle and Power Purchase Agreements (PPAs)
The project life is set by the contract, not by the plant. A PPA with a distribution company or another offtaker fixes the tariff and the term, which is commonly around 25 years for utility-scale solar. Model the construction period, the commissioning date and any delay allowance separately from the operating years. A delay matters more than it looks. A four-month slip removes about a third of the first year’s revenue and about 1.3 per cent of revenue over the full term, before any penalty the PPA imposes for late commissioning.
Read the PPA for the clauses that move the revenue line: the tariff and whether it escalates, the deemed generation clause, curtailment and the payment security mechanism. Late payment surcharge rules and receivable days from state utilities decide how much working capital the project needs. Lenders in Mumbai and Pune usually ask for the same clauses, so put each term in the model as an input with its source noted.
A developer in Ahmedabad signs a 25-year PPA at a fixed tariff, with a commissioning deadline twelve months after signing. The model shows that a four-month delay cuts first-year revenue by a third, and the sponsor sees that cost in the base case rather than as a note at the back of the model.
Key Capital Expenditure (CAPEX) and Funding Assumptions
CAPEX per megawatt is the largest input in a solar model. It is built from module, inverter, mounting and balance of system costs plus the EPC contract, and it is funded by a mix of debt and equity. A common planning norm is 70 per cent debt and 30 per cent equity, but the lender’s own terms decide the actual structure.
Structuring the Standard 70:30 Debt-to-Equity Ratio
The 70:30 debt-to-equity split comes from the normative capital structure used in the central regulator’s tariff orders for renewable projects. It is a benchmark for tariff setting, not a lending commitment. Banks and financial institutions set their own leverage on the project’s cash flows, using the debt service coverage they require and their view of the PPA counterparty. A project with a weak offtaker may get less debt, and a project with a strong contract may get more.
Model the debt in tranches: construction debt that converts to term debt on commissioning, a repayment schedule that matches the PPA term, and a debt service reserve. Calculate interest during construction and upfront fees, because both add to the funding need. Solve for equity as the balance, then check that the sponsor’s equity cheque matches what the project needs at each stage.
A lender in Mumbai offers term debt of 70 per cent of a Rs 400 crore project in a state where the offtaker has a strong payment record. A sponsor in Pune with a weaker offtaker can raise only 60 per cent debt. The model shows that the second case needs Rs 40 crore more equity, and it sets out the equity return under each case so the choice of counterparty is priced before the bid.
Modeling Cost per MW: Modules, Inverters, and EPC Costs
Build CAPEX per MW from the bill of materials, not from one benchmark figure. Modules, mounting structures, inverters, transformers, cables, land development, evacuation infrastructure and the EPC margin each move at a different rate. Module prices have been volatile, and inverter and balance of system costs change with the supplier and the import duty position, so the model should keep them apart. Take current quotes from at least two EPC contractors and compare them with recent tender results in the same state.
Include the costs that sit outside the EPC contract: land lease or purchase, grid connection and substation charges, insurance during construction, owner’s engineer fees and the development fee. Grid connection costs differ by state and by substation, so the location should be an input. Keep a contingency line, because an unexpected interconnection upgrade can move the project cost more than a change in module prices.
A Vadodara developer builds a 20 MW plant. The EPC quote is close to benchmark, but a substation upgrade adds Rs 0.4 crore per MW, or Rs 8 crore on the plant. On an illustrative project cost of Rs 4 crore per MW, that is 10 per cent more, and debt sized at 70 per cent rises by Rs 5.6 crore.
Bidding for a solar project?
Talk to Elite Valuation about checking your tariff, CAPEX and cash flow assumptions before you submit the bid.
Discuss your solar modelFinancial Modeling | Tariff Analysis | Project Finance
Revenue Forecasting and Operational Assumptions
Revenue in a solar model is output multiplied by tariff, and output comes from the capacity utilization factor adjusted for degradation and losses. Levelized cost of energy (LCOE) then tests whether the tariff covers the cost of the plant over its life. Both need a site-specific source, not a national average.
Capacity Utilization Factor (CUF) and Degradation Rates
The capacity utilization factor (CUF) is the energy a plant produces in a year divided by what it would produce at full capacity for all 8,760 hours. Annual energy in MWh equals MW multiplied by 8,760 multiplied by CUF. CUF depends on irradiance, temperature, module orientation and tracker use, and losses for soiling, wiring and inverter efficiency reduce it further. A site-specific yield study from a recognised consultant should set the first-year figure, and the lender’s advisers will test it against satellite irradiance data.
Module output falls over time. Manufacturers warrant a minimum output after 25 years, and the annual decline in early years is usually a fraction of one per cent. Apply the degradation rate from the module datasheet and warranty, and show output for each year so the lender can see the line. Soiling losses are high at some sites in Rajasthan and Gujarat, so tie them to a cleaning schedule with its own cost.
A Gurugram adviser reviews a 15 MW plant in Rajasthan. The yield study gives a CUF of 23 per cent before soiling. After a soiling loss and a cleaning plan, the model uses 21 per cent, and year-one energy is about 2,600 MWh lower than the first draft suggested. The illustrative figures are chosen to show the mechanics, not a benchmark for any site.
Levelized Cost of Energy (LCOE) and Tariff Determination
LCOE is the present value of all costs over the plant’s life divided by the present value of the energy it produces over the same period. It gives a single cost per unit that can be set against the tariff. Costs include CAPEX, operating costs, insurance, land lease, major repairs and any inverter replacement. Discount at the cost of capital the project is financed on, not at a rate picked for convenience.
A tariff bid is set by the auction result, not by the model. The model’s job is to show the tariff the project needs for its target equity return, and whether the bid leaves room for error. A project that bids close to its LCOE has no cushion for a cost overrun, a weaker CUF or slower payment. Show the bid tariff, the break-even tariff for the target return, and the tariff at which lender coverage ratios are breached.
A Delhi sponsor plans to bid only 2 per cent above its LCOE. In the illustration, a 5 per cent CAPEX overrun takes the equity IRR below the sponsor’s hurdle rate, so the bid team tests a higher tariff and a lower capital cost before submission.
Tax Shields, Subsidies, and Investor Returns
Tax benefits, subsidies and viability gap support change the cash flow and the return, but each depends on a rule that may have changed. Check every item against the current law and the scheme text. Then report project IRR and equity IRR separately, because they answer different questions for different readers.
Factoring MNRE Subsidies, Viability Gap Funding (VGF), and Tax Holidays
Central and state schemes for solar have changed several times. Support may come as a capital subsidy, viability gap funding, concessional land or a state incentive on electricity duty, and each has its own eligibility, timing and clawback terms. Model a subsidy only when the scheme is open to the project and its conditions are met, and show the receipt date, because a grant received late can change the funding plan.
The income tax holiday for power generation under section 80-IA of the old Act applied to undertakings that began operating before 1 April 2017, and a new project should not assume it. Accelerated depreciation on solar plant is the main tax shield available now. The Income-tax Act, 2025, which took effect on 1 April 2026, carries depreciation into renumbered schedules, so confirm the rate and any first-year allowance there before the model relies on them. Check whether the benefit can be used against the project’s taxable income or must be carried forward.
A Pune sponsor models a state support payment and accelerated depreciation for a 10 MW plant. The scheme’s funds are then reported as exhausted, so the model removes the payment and reruns the case. The depreciation schedule stays in, and the sponsor sees how much of the return depended on the payment.
Calculating Project IRR vs. Equity IRR
Project IRR uses cash flows before debt: CAPEX as the outflow, and operating cash flow plus any residual value as the inflows. It tests whether the asset earns its cost of capital, whatever the financing. Equity IRR uses the cash flows that reach shareholders after debt service, tax and reserve accounts, and it tests the sponsor’s return. A project can show a healthy project IRR and a weak equity IRR if the debt is expensive, or the reverse if the debt is cheap but the lender sweeps the cash.
Report both, with the debt schedule that links them. Show the debt service coverage ratio (DSCR) for each year and the minimum across the loan life, because a lender in Mumbai will test the minimum against its covenant. Keep the tax computation in the same model rather than a separate file, so a change in depreciation flows through to the equity return.
A Bengaluru infrastructure fund reviews a 50 MW plant with a project IRR of 11 per cent and an equity IRR of 14 per cent, after debt at 9 per cent. The lender then requires a debt service reserve equal to six months of debt service. In the illustration, the equity IRR falls by about a point, and the fund sees the cost of the reserve in its return.
Want to see how tax and debt structuring change your equity IRR?
Speak with Elite Valuation’s renewable energy modelling team about the structure that fits your project and your lenders.
Speak with our modelling teamFinancial Modeling | Debt Structuring | Renewable Energy
Frequently Asked Questions (FAQs)
What is the standard debt-equity ratio for solar projects in India?
The 70:30 split is a benchmark from the normative capital structure in the central regulator’s tariff orders for renewable projects, and it is often quoted as the standard. It is not a lending rule. Lenders set debt by the project’s cash flows, the strength of the offtaker and the coverage ratios they require. Use 70:30 as a reference point only, and check the current order before quoting it.
How do you calculate the Levelized Cost of Energy (LCOE)?
LCOE is the present value of all costs over the plant’s life divided by the present value of the energy it produces over the same period, both discounted at the project’s cost of capital. Costs include CAPEX, operating and maintenance, insurance, land lease and major replacements. Energy is annual output reduced for degradation over the life. Compare the result with the tariff and with the break-even tariff for the target equity return.
What is the Capacity Utilization Factor (CUF) in solar modeling?
CUF is the energy a plant produces in a year divided by the energy it would produce at full output for all 8,760 hours. It reflects irradiance, losses, temperature and tracker use. A site-specific yield study should set the first-year CUF, and the model should show each loss on its own line so that a lender can test each one.
How do panel degradation rates impact long-term revenue forecasts?
Each year of degradation reduces output slightly, and the effect compounds over 25 years. Tariffs are fixed by the PPA and cannot rise to offset lower output, so the revenue loss is real. Take the rate from the module datasheet and warranty, apply it year by year, and show the revenue effect beside the base case.
How does accelerated depreciation under the Income-tax Act, 2025 improve solar project viability?
Accelerated depreciation allows a larger deduction in the early years of an asset’s life, which lowers early tax and improves cash flow when a project most needs it. The Income-tax Act, 2025, which took effect on 1 April 2026, carries the rules into renumbered schedules. Confirm the rate and eligibility for solar plant there, and check whether the deduction can be used in the year or carried forward.
What are typical O&M (Operations and Maintenance) escalation rates?
Operations and maintenance contracts usually include an annual escalation set in the contract itself. Planning models often assume a few per cent a year, and the model should test a higher rate as well. Include module cleaning, inverter servicing and insurance, and show each cost. Confirm the escalation against the O&M quotes you hold rather than a published figure.
How do you model working capital for a utility-scale solar plant?
Working capital in a solar plant is mostly receivables from the distribution company or other offtaker. Model receivable days from the PPA’s payment terms, add any delay seen in the sector, and apply late payment surcharge only where the contract provides it. Hold a reserve for debt service and show the cash needed to bridge delayed payments. Payment delay is often what strains a project that looks sound on paper.
What is the difference between Project IRR and Equity IRR?
Project IRR is the return on the asset before debt. Equity IRR is the return to the sponsor after debt service and reserves. The first tests whether the plant earns its cost of capital, and the second tests what shareholders receive. Report both, with the debt schedule linking them, because a project can look strong on one measure and weak on the other.
Want a solar model that a lender can test against its own assumptions?
Contact Elite Valuation to discuss the scope, the inputs and the sources we would use for your project.
Contact Elite ValuationFinancial Modeling | Project Finance | Lender Review
Sources
- CERC Renewable Energy Tariff Regulations, 2024: normative financial principles, including the 70:30 debt-equity benchmark.
- Income-tax Act, 2025: official text as amended by the Finance Act, 2026.
- Income-tax Rules, 2026: notified rules and depreciation schedules.
- Ministry of New and Renewable Energy: official solar-energy scheme resources.
- ICAI compendium of Indian Accounting Standards: Ind AS 115 and Ind AS 16.
- Historical reference: section 80-IA of the Income-tax Act, 1961, including the commencement condition for power-generation undertakings.
Disclaimer. This article provides general information, not legal, tax, accounting or investment advice. Scenarios and figures are hypothetical illustrations, not client results or industry benchmarks. Project terms, applicable tax treatment and subsidy eligibility depend on the project and current rules. Obtain advice appropriate to your circumstances.